Working time calendar for 2020 - download


Production calendar 2020 in horizontal orientationIn horizontal orientation
In vertical orientation

DOWNLOAD Production calendar for 2020 in horizontal orientation (PDF, 47 kb) Production calendar for 2020 in vertical orientation (PDF, 30 kb)

Calendar with 5-day week

Working time standards

Holidays and shortened days

Transfers of days off

Calendar with 6-day week

A production calendar is a document that defines working time standards, indicating weekends, holidays and pre-holiday days. Based on this data, work schedules are drawn up, including a document recording the actual time worked, the data of which at the end of the period determines the size of the salary. Our calendar is formatted in such a way that it is easy and understandable to navigate even for an inexperienced accountant or personnel officer.

Quarterly production calendar for 2020 with a 5-day week

31 – holiday

31 – pre-holiday day

31 – day off

31 – working day

Short version

I quarter 2020

January
MonTueWedThuFriSatSun
2627282930311
2345678
9101112131415
16171819202122
23242526272829
303112345
February
MonTueWedThuFriSatSun
303112345
6789101112
13141516171819
20212223242526
272812345
March
MonTueWedThuFriSatSun
272812345
6789101112
13141516171819
20212223242526
272829303112
JanuaryFebruaryMarchI quarter
Number of days in the period
Calendar31283190
workers17182257
Weekends1410933
Number of working hours per week
40 hours136143175454
36 hours122,4128,6157,4408,4
24 hours81,685,4104,6271,6

II quarter 2020

April
MonTueWedThuFriSatSun
272829303112
3456789
10111213141516
17181920212223
24252627282930
May
MonTueWedThuFriSatSun
1234567
891011121314
15161718192021
22232425262728
2930311234
June
MonTueWedThuFriSatSun
2930311234
567891011
12131415161718
19202122232425
262728293012
AprilMayJuneII quarterI half of the year
Number of days in the period
Calendar30313091181
workers20202161118
Weekends101193063
Number of working hours per week
40 hours160160168488942
36 hours144144151,2439,2847,6
24 hours9696100,8292,8564,4

III quarter 2020

July
MonTueWedThuFriSatSun
262728293012
3456789
10111213141516
17181920212223
24252627282930
31123456
August
MonTueWedThuFriSatSun
31123456
78910111213
14151617181920
21222324252627
28293031123
September
MonTueWedThuFriSatSun
28293031123
45678910
11121314151617
18192021222324
2526272829301
JulyAugustSeptemberIII quarter9 months
Number of days in the period
Calendar31313092273
workers21232165183
Weekends10892790
Number of working hours per week
40 hours1681841685201462
36 hours151,2165,6151,24681315,6
24 hours100,8110,4100,8312876,4

IV quarter 2020

October
MonTueWedThuFriSatSun
2526272829301
2345678
9101112131415
16171819202122
23242526272829
303112345
November
MonTueWedThuFriSatSun
303112345
6789101112
13141516171819
20212223242526
27282930123
December
MonTueWedThuFriSatSun
27282930123
45678910
11121314151617
18192021222324
25262728293031
OctoberNovemberDecemberIV quarterII half of the year2017
Number of days in the period
Calendar31303192184365
workers22212164129247
Weekends99102855118
Number of working hours per week
40 hours17616716851110311973
36 hours158,4150,2151,2459,8927,81775,4
24 hours105,699,8100,8306,2618,21182,6

PRODUCTION CALENDAR FOR 2020

Go to the archive (2000-2017) >>>

Calendar 2020

Months of the year Days of the weekJanuaryFebruaryMarchApril
Monday 2 9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24
Tuesday 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25
Wednesday 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26
Thursday 5 12 19 26 2 9 16 23 2 9 16 23 30 6 13 20 27
Friday 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28
Saturday 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29
Sunday 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30
Months of the year Days of the weekMayJuneJulyAugust
Monday 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28
Tuesday 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29
Wednesday 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Thursday 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31
Friday 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25
Saturday 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
Sunday 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27
Months of the year Days of the weekSeptemberOctoberNovemberDecember
Monday 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
Tuesday 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26
Wednesday 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27
Thursday 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
Friday 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
Saturday 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30
Sunday 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31

*Non-working holidays.

** According to the Resolution of the Council of Ministers of the Republic of Belarus dated November 9, 2016 No. 912 “On the transfer of working days in 2020”, working days are postponed: from Monday January 2 to Saturday January 21, from Monday April 24 to Saturday April 29, from Monday May 8 to Saturday 6 May, Monday 6 November to Saturday 4 November.

For information

April 16—Catholic and Orthodox Easter.

April 25—Radunitsa.

Production calendar for 2020 for a five-day work week
Months and other periods of the yearAmount of daysEstimated standard working time (in hours)
calendarworkers (regular and pre-holiday)non-working days (weekends and holidays)with a 40 hour work weekwith a 35 hour work week
January 31 22 (21 + 1) 9 (7 + 2) 175 153
February 28 20 8 160 140
March 31 22 (21 + 1) 9 (8 + 1) 175 153
I quarter 90 64 26 510 446
April 30 19 (18 + 1) 11 (10 + 1) 151 132
May 31 21 (20 + 1) 10 (8 + 2) 167 146
June 30 22 8 176 154
II quarter 91 62 29 494 432
1st half of the year 181 126 55 1 004 878
July 31 20 11 (10 + 1) 160 140
August 31 23 8 184 161
September 30 21 9 168 147
III quarter 92 64 28 512 448
October 31 22 9 176 154
November 30 21 (20 + 1) 9 (8 + 1) 167 146
December 31 20 11 (10 + 1) 160 140
IV quarter 92 63 29 503 440
2nd half of the year 184 127 57 1 015 888
2017 365 253 (248 + 5) 112 (103 + 9) 2 019 1 766
Production calendar for 2020 for a six-day work week
Months and other periods of the yearAmount of daysEstimated standard working time (in hours)
calendarworkers (regular and pre-holiday)non-working days (weekends and holidays)with a 40 hour work weekwith a 35 hour work week
January 31 25 (24 + 1) 6 (4 + 2) 168 146
February 28 24 4 160 140
March 31 26 (25 + 1) 5 (4 + 1) 173 151
I quarter 90 75 15 501 437
April 30 24 (23 + 1) 6 (5 + 1) 157 138
May 31 25 (24 + 1) 6 (4 + 2) 166 145
June 30 26 4 174 152
II quarter 91 75 16 497 435
1st half of the year 181 150 31 998 872
July 31 25 6 (5 + 1) 165 145
August 31 27 4 181 158
September 30 26 4 172 151
III quarter 92 78 14 518 454
October 31 26 5 174 152
November 30 25 (24 + 1) 5 (4 + 1) 166 145
December 31 25 6 (5 + 1) 165 145
IV quarter 92 76 16 505 442
2nd half of the year 184 154 30 1 023 896
2017 365 304 (299 + 5) 61 (52 + 9) 2 021 1 768
For information

For a more detailed study, see the commentary

.

Working time standards for 2020 in the table

Below is a summary table of the number of calendar days, working days, weekends and the number of working hours for 40-, 36-, 24-hour work weeks by month, quarter, half-year and in general for the entire 2020. Keep it for yourself.

PeriodAmount of daysWorking hours per week
CalendarworkersWeekends40 hours36 hours24 hours
January311714136122,481,6
February281810143128,685,4
March31229175157,4104,6
1st quarter905733454408,4271,6
April30201016014496
May31201116014496
June30219168151,2100,8
2nd quarter916130488439,2292,8
1st half of the year18111863942847,6564,4
July312110168151,2100,8
August31238184165,6110,4
September30219168151,2100,8
3rd quarter926527520468312
October31229176158,4105,6
November30219167150,299,8
December312110168151,2100,8
4th quarter926428511459,8306,2
2nd half184129551031927,8618,2
201736524711819731775,41182,6

FILES

Where and how are working time standards applied?

The standard working time is determined by the total number of hours that need to be worked over a certain calendar period.

This indicator is used to approve the operating mode of the enterprise. The standard was developed taking into account the adequate distribution of the workload on the employee, preventing the arbitrariness of the employer in terms of unauthorized increase in the number of working hours.

The Labor Code defines the duration of working hours - 40 hours per week for full-time employment (Article 91). Article 92 specifies the duration of a shortened working day for adolescents under 16 years of age, young people from 16 to 18 years of age, disabled people, hazardous workers and teachers.

The length of the working week for each category of citizens allows us to calculate the standard working hours for any month.

To do this, take the weekly norm of working hours, divide by 5 (the number of working days in a classic 5-day week), and then multiply by the sum of working days of a particular calendar month (total number of days minus weekends and holidays). The result is the standard working hours for the billing month.

Important! If there were holidays in the month, then it should be taken into account that the weekday preceding them is always 1 hour shorter than the standard working hours. Thus, from the number of days obtained by the specified formula, one more hour must be subtracted for each day preceding the holiday.

In this simple way, the number of hours that each employee must work to receive 100% of the salary is obtained. Based on the ratio of days actually worked to the standard for a particular month, the amount of wages is determined.

Working time standards are used to organize the work regime of workers of any profession. The production standard applied at manufacturing enterprises is, in fact, also a type of standardization of working time.

How to determine working hours

Standard working hours are usually determined depending on how long working hours are established during a five-day work week with two days off (Saturday and Sunday) and based on the length of the daily work shift. This procedure is determined by Order of the Ministry of Health and Social Development of Russia dated August 13, 2009 N 588n.

If we work a 40-hour work week, then the standard working time will be 8 hours. With a 36-hour work week it will be equal to 7.2 hours, and with a 24-hour work week it will be 4.8 hours.

Part 1 of Article 95 of the Labor Code of the Russian Federation states that the duration of the work shift that precedes a holiday is reduced by one hour. So, in 2020 we will work one hour less on days such as February 22, March 7 and November 3. Moreover, this standard working time applies to all work and rest regimes.

Holidays and shortened days according to the calendar

Below is a table from which it is clearly seen that in 2017 there will be several “long” weekends. We also note that a shortened working day involves reducing working time by 1 hour.

HolidaysHolidayShortened days
January 1-6,8New Year holidays
Jan. 7Nativity
February 23-26Defender of the Fatherland DayFebruary 22
March 8International Women's DayMarch 7
April 29 - May 1Labour Day
May 6-9Victory Day
June 10-12Russia Day
November 4-6National Unity Daythe 3rd of November

How many working days did the working calendar contain - 2020

Non-working days included in the working time calendar for 2016 were classified as such thanks to the Decree of the Government of the Russian Federation “On the transfer of days off in 2020” dated September 24, 2015 No. 1017. In addition, the 2016 calendar contains dated working days and days off due to employees and holidays.

Let us note what working time standards were proposed in the working time calendar - 2016 :

  • number of calendar days - 366;
  • workers - 247;
  • weekends and holidays - 119.

Time spent working:

  • with a 40-hour week it was 1,974 hours per year;
  • at 36 hours - 1,776 hours;
  • at 24 hours - 1,183 hours.

The working time calendar for 2020 is posted on our website.

Working time calendar for 2020

Postponement of holidays in 2020

In 2020, January 1 and 7, as well as November 4 fall on weekends. Therefore the transfers will be as follows:

  • From Sunday January 1st to Friday February 24th
  • From Saturday January 7th to Monday May 8th
  • From Saturday November 4th to Monday November 6th

This follows from the text of the Decree of the Government of the Russian Federation of August 4 No. 756 “On the transfer of days off in 2020” signed by D.A. Medvedev.

How and why are weekends postponed?

There are 14 official holidays in Russia. Every year the Government adopts another resolution on their transfer. Such an event is carried out in order to optimize the production calendar and avoid a “ragged” work schedule. There are a few simple transfer rules:

  • If a holiday falls on a weekend, it is moved to the working day following that weekend.
  • Working hours on the day preceding a holiday are reduced by 1 hour.
  • In order for workers to be able to rationally use their rest days, weekends are sometimes transferred to weekdays. For the same reasons, it is allowed to transfer 2 days off during the New Year holidays to any other month.

If you are from the Republic of Tatarstan or Bashkortostan: Production calendar 2020 for the Republic of Tatarstan Production calendar 2020 for the Republic of Bashkortostan

All Russian holidays of 2020 in a single table

Russia occupies one of the leading places in the world in terms of the number of holidays per year. I would like to immediately note that not every holiday has the status of a day off. To become one, you need a corresponding Decree signed by the President of the Russian Federation. We have combined all the 2020 holidays into one single table, and by looking at it, you can immediately be convinced that there will always be a reason!

Download calendar files for printing on a printer (A4 format)

Choose the most convenient format for printing your calendar:

DOWNLOAD CALENDAR FILES7 files


Download production calendar in JPG:


,


,


,


(on 4 pages) (on 4 pages)

Save it, it will come in handy:

Production calendar with a six-day work week

The law provides that some enterprises can establish a 6-day working week (Article 100 of the Labor Code of the Russian Federation). With this work schedule, the day off will be Sunday (Article 111 of the Labor Code of the Russian Federation). At the same time, the number of working hours on the eve of a day off cannot be more than 5 hours (Article 95 of the Labor Code of the Russian Federation). The limitation of 40 working hours with a 6-day working week remains (Article 91 of the Labor Code of the Russian Federation), therefore in practice the following scheme for distributing the number of hours by day of the week is often used, in the order from Monday to Saturday: 7+7+7+7+7 +5=40.

FILES

Work schedules provided for by the Labor Code of the Russian Federation

The classic work process model provides for a 5-day work week with 2 days off and a working day of 8 hours. Not all enterprises can work according to this scheme, so there are other work schedule options:

  • Irregular working hours. For employees who stay at work after the end of the working day or come to work before it starts. The Labor Code of the Russian Federation strictly defines the list of positions for which this is permissible.
  • Shift work. Introduced in enterprises that operate longer than the maximum permissible daily work duration.
  • Flexible schedule. Provides the ability to select the start time, end time and duration of the working day. The main thing is to develop the required hours per month and year.
  • Fragmented workday. A working day with a break breaking it up into parts. In total, it cannot exceed the duration of daily work permitted by the Labor Code.

Important! In work schedules other than the classic five-day workday, the summarized accounting method is used. In this case, it is not the weekly standard that is taken into account, but the monthly or even annual one. The duration of working hours for the period, on average, must be equal to the duration of the working day permitted by the Labor Code.

Why do you need a production calendar?

Employees of HR departments and accounting departments cannot do without a production calendar. However, this document is also used by other employees of various companies and enterprises. So, to summarize, we can highlight why it is needed:

  • Drawing up a work schedule. Using a production calendar allows you to take into account the number of weekends and working days in the month for which the schedule is being drawn up.
  • Determination of the norm of working time for each period. The specifics of calculating this indicator will be discussed below.
  • Calculation of wages, vacation and sick leave benefits. Based on the working time sheet at the end of the period, the ratio of actually worked time to planned time is determined. The resulting values ​​help calculate the amount of monthly payments and bonuses.
  • Vacation planning. Employees, having familiarized themselves with the production calendar, can choose the best time for vacation, determine the dates of short-term trips, and purchase tickets and vouchers in advance.
Rating
( 1 rating, average 4 out of 5 )
Did you like the article? Share with friends:
Business guide